Experience of technocrats working with KMN Engineering Consultants hydel sectors during their services are following: –
S.No. | Name of Hydel Project | Department/Company | Location State | Current status |
1. | Kurhed (4.5 MW) | HIMACHAL HYDRO | HP | Commissioned |
2. | Tulang(3 MW) | HIMACHAL HYDRO | HP | Successfully commissioned since July 2014 |
3. | Kalheh(2.5 MW) | VKG | HP | At NOCs stage |
4. | Shat(5 MW) | SKB | HP | Various NOCs obtained except forest clearance which is under process and in final stage |
5. | Chharor(3 MW) | SKB | HP | Various NOCs obtained except forest clearance which is under process and in final stage |
6. | Kurpan(4.8MW) | HIMPRABHA | HP | All NOCs obtained and ready for construction. |
7. | Kuril (5 MW) | SAHU HPPL | HP | Survey / investigations, hydraulic studies, cost analysis, detailed structural designs and tender documentation for all Civil/ Mechanical/ Electrical works complete. Ready for construction. |
8. | Kurtha (5 MW) | SAHU HPPL | HP | Successfully commissioned since October 2014 |
9. | Chonned (15MW) | PARVAT HPPL | HP | Survey and investigation works complete. All NOCs obtained. |
10. | SJVNL (412 MW) | SJVNL | HP | Consultancy for Structural design/ preparation of construction/fabrication drawing for 1 no. rope drum hoist and 1 no. portal gate for an opening of size 10.15m*10.15m at portal of spill tunnel for Rampur hydel project i/c its electrical arrangements complete. Project successfully commissioned. |
11. | Swad (5 MW) | Micro Hydro Pvt. Ltd. | HP | Due diligence at construction stage |
12. | Surah (1.5 MW) | Micro Hydro Pvt. Ltd. | HP | Due diligence at construction stage |
13. | Neri (5 MW) | M/S ArchitButel | HP | Prepared tenders, structure design and prepared of structure for civil/hydro-mechanical equipments. Ready for construction. |
14. | Kurpan Bagipul (1 MW) | Micro Hydro Pvt. Ltd. | HP | Revised DPR prepared and submitted for TEC. |
15. | Baleni Ka Nallah(2 MW) | Manimahesh Urja | HP | DPR prepared and submitted for TEC. |
16. | Panchpula(0.5 MW) | ERS | HP | DPR prepared and submitted for TEC. |
17. | Shikari Mata (0.3MW) | Shepmandi | HP | DPR prepared and submitted for TEC. |
18. | Dev Kalakameshwar (0.15 MW) | Shepmandi | HP | DPR prepared and submitted for TEC. |
19. | Panjoud (0.5 MW) | Shepmandi | HP | DPR prepared and submitted for TEC. |
20. | Kanda (400 KW) | M/S Bhagwati Power Projects. | HP | DPR prepared and submitted for TEC. |
21. | Bharog (0.250 MW) | M/S Ramu Ram | HP | DPR prepared and submitted for TEC. |
22. | Megal (0.08 MW) | M/S Ramu Ram | HP | DPR prepared and submitted for TEC. |
23. NEW | Around 30 small hydel projects from 120 Kw to 10 Mw capacities work have been awarded by Kargil Renewable Energy Development Agency (KREDA), Distt. Kargil, Govt. of Jammu & Kashmir | Kargil Renewable Energy Development Agency (KREDA) | J&K | Planning/survey and investigation work have been done for 30 hydel projects in Zanskar river. All the projects are in Zanskar river at the elevation in between 3500m to 4500m in district kargil. All 30 PFRs for these projects have been prepared and submitted to KREDA and further to MNRE for their approval. Out of these 30 projects, 13 have been approved by IIT roorki for construction. We have prepared DPRs complete in all respect for these 13 projects to KREDA for further n/a at their end. |
24. | Nogli(3.0MW) | Kamaksha Electrical power project Pvt. Ltd. | HP | Prepared DPRs, got its TEC for Energy Department of Govt. of H.P Detailed Structural Design for various Civil/Mechanical works. At presently under constructions. |
25. | Nazonga(0.9MW) | DEV BHUMI Hydro power project Pvt. Ltd. | HP | Prepared DPRs, got its TEC for Energy Department of Govt. of H.P Detailed Structural Design for various Civil/Mechanical works. At presently under constructions. |